Secure long-lead equipment before fixing the tariff
With turbine lead times around six years and transformer waits doubled, the equipment reservation is now a critical-path item. Owners need turbine slot agreements, escalation mechanisms and delivery guarantees in place before tariff bids or PPA pricing are fixed, and lenders will test whether the EPC price and schedule reflect the reservation actually held rather than a nominal market lead time.
Treat grid access as a bankability risk
Non-firm connections and grid-enhancing technologies can bring projects online earlier, but they shift curtailment risk to the project. Energy yield and revenue cases should model curtailment explicitly, connection agreements should define compensation where it exists, and debt sizing should rest on a curtailment case that a lender's technical adviser can reproduce, with sensitivities for delayed network reinforcement.
Data-center offtake needs its own contract design
Supplying large digital loads, especially onsite, involves overbuilding of 30% to 70% for reliability, a buyer whose own planning horizon may be shorter than the plant's life, and grid interconnection that may come later. Offtake terms, take-or-pay levels, buyer credit support and the treatment of surplus capacity need to be agreed before financing, not after.
Value hybrid portfolios on peak and evening capacity
Solar now drives most new supply, while batteries are becoming cheap enough to move a meaningful share of it into the evening. Feasibility studies for hybrid plants should value capacity at the hours when the system needs it, using hourly dispatch and battery degradation assumptions, rather than annual energy totals. Augmentation costs and the split of revenues between energy shifting and capacity payments should be visible in the model.
Use credit enhancement where the cost of capital is high
In markets where capital costs are double those in advanced economies, guarantees and multilateral participation materially widen the pool of private lenders. Structures should be designed from the outset to meet the eligibility rules of guarantors and development lenders, including currency, payment security and termination provisions, so that the project is not restructured when a guarantor joins late in the process.