DKC carried out the financial, tax, and legal review of the 728 MW Phou Ngoy hydropower project for Dohwa Engineering.
ABOUT THE PROJECT
Phou Ngoy is a proposed 728 MW hydropower plant on the Mekong mainstream in Champassak province, southern Laos, about 18 km south of Pakse, and is the seventh of nine existing or planned large hydropower projects on the Mekong mainstream. The lead developer is Thailand's Charoen Energy and Water Asia. The project cost has been reported at US$2.4 billion, with power expected to be sold to Thailand.
As reported in April 2022, Korea Western Power and Doosan Heavy Industries & Construction were slated to build the dam, and no power purchase agreement had yet been signed. Lao officials planned to submit the project to the Mekong River Commission for prior consultation, in which member countries assess cross-border effects on river flow, water quality, and environmental and social conditions. Completion was targeted for 2029.
DKC'S ROLE
Financial, tax, and legal review for Dohwa Engineering.
Scope
- Financial analysis
- Tax review
- Legal review
CASE STUDY
THE CHALLENGE
Dohwa Engineering needed an independent financial, tax, and legal view of the 728 MW Phou Ngoy hydropower project in Laos.
THE SOLUTION
DKC carried out the financial analysis and the tax and legal review of the project.
THE RESULT
Financial, tax, and legal review delivered to Dohwa Engineering (November 2021 to May 2022).
WHAT IT MEANS FOR CLIENTS Tax and legal terms in the host country can change a hydropower project's returns as much as its engineering.