DKC carried out the financial, tax, and legal review of a 30 MW small hydropower project in Sulawesi for Dohwa Engineering.
ABOUT THE PROJECT
Small hydropower in Indonesia is developed mainly by independent power producers selling to the state utility PLN. Since Presidential Regulation 112 of 2022, hydropower tariffs are negotiated with PLN under a ceiling price set in the regulation, with no escalation during the power purchase agreement and approval required from the energy ministry. PLN's electricity supply business plan for 2025 to 2034 adds 11.7 GW of hydropower, including pumped storage, and expects about 73% of new plants to be developed by private producers.
DKC'S ROLE
Financial, tax, and legal review for Dohwa Engineering.
Scope
- Financial analysis
- Tax review
- Legal review
CASE STUDY
THE CHALLENGE
Dohwa Engineering needed a financial, tax, and legal review of a 30 MW small hydropower project in Sulawesi.
THE SOLUTION
DKC reviewed the project's financial case together with the Indonesian tax and legal framework that applies to it.
THE RESULT
Financial, tax, and legal review delivered to Dohwa Engineering (December 2021 to April 2022).
WHAT IT MEANS FOR CLIENTS Financial, tax, and legal questions reviewed together, as lenders will review them, for a small run-of-river project.
PUBLIC INFORMATION ON THE PROJECT
- ABNR — Long-awaited Presidential Regulation signals transition to greener energy in Indonesia (Oct 2022) ↗
- Enerdata — Indonesia aims to add 69.5 GW of new power capacity between 2025 and 2034 (May 2025) ↗
"About the project" summarizes published information on the project and its market. It does not describe DKC's findings; DKC's role is described separately above.